STH 69 Construction Project Update 8/04/22

Construction Update for STH 69 and the upcoming weeks:

  • Bridge work continues into September on the Badger Mill Creek bridge. STH 69 is closed from Manhattan Drive to Pine Row.
  • Grading operations are occurring on mainline from Himsel Road to County PB, and including County PB
  • Grading of side roads is anticipated in the month of August
  • Aggregate placement will continue in the month of August
  • The lanes are narrow as crews work on and through the existing roadbed.
  • Grading of the new roundabout at CTH PB has started, and will continue including construction of the new box culvert, and storm sewer work
  • Concrete curb and gutter work is anticipated later in August
  • Utility work continues south of Paoli to Belleville

A reminder that CTH PB at STH 69 in Paoli is closed to all traffic.

Paoli Road to the west is permanently removed from STH 69, and a cul-de-sac will be built.  There is a temporary connection to Paoli Road to the east, but this will be permanently removed in the near future.

STH 69 is closed to thru traffic.  Access is allowed for residents and businesses that have an origin or destination on the project. It is highly suggested to use your closest access to STH 69 to get to a driveway. Large trucks need to use appropriate truck routes.

Please slow down, and the construction crew has the right-of-way.

A signed detour route is posted and follows WIS 92, WIS 78 and US 18/151.

Project Website:  https://projects.511wi.gov/wis69/

If you have any comments or questions, please reach out to Kim Ballweg at 608.212.5191 or ballwegk@AyresAssociates.com.

Thank you for your patience and understanding throughout the construction season. The section from Paoli to Verona is anticipated to open around November 1st.


Public Hearing

Town of Montrose

PUBLIC HEARING

1341 Diane Ave., Belleville WI 53508

Tuesday August 2, 2022, at 7:00 PM

Regular Board Meeting to follow

 

  1. Discussion and/or Recommendation on Vacation of 49.5 foot wide strip of land that is part of the SE and SW quarters of the SW quarter, Section 20, Town 5 North, Range 8 East, Town of Montrose, Dane County, Wisconsin.

Commencing at the South Quarter corner.  Vacating approximately 786 feet of Feller Road north of Pioneer Cemetery.

 


STH 69 Construction Project Update 7/20/22

The STH 69 project is continuing to make progress. The photo is looking north towards Sunset Drive:

Construction Update for STH 69 and the upcoming weeks:

  • Bridge work continues into September on the Badger Mill Creek bridge. STH 69 is closed from Manhattan Drive to Pine Row.
  • Grading of the new roadway is completed from Pine Row to south of Sunset and rock is placed (see photo above)
  • Grading operations are occurring and will continue from south of Sunset to CTH PB.
  • The lanes are narrow as crews work on and through the existing roadbed.
  • Grading of the new roundabout at CTH PB has started, and will continue
  • Culvert pipe work continues
  • Construction of the box culvert begins the week of July 25th, and the old bridge will be removed
  • Utility work continues south of Paoli to Belleville

A reminder that CTH PB at STH 69 in Paoli is closed to all traffic.

STH 69 is closed to thru traffic.  Access is allowed for residents and businesses that have an origin or destination on the project. It is highly suggested to use your closest access to STH 69 to get to a driveway. Large trucks need to use appropriate truck routes.

Please slow down, and the construction crew has the right-of-way.

A signed detour route is posted and follows WIS 92, WIS 78 and US 18/151.

Project Website:  https://projects.511wi.gov/wis69/

If you have any comments or questions, please reach out to Kim Ballweg at 608.212.5191 or ballwegk@AyresAssociates.com.

Thank you for your patience and understanding throughout the construction season.

 

 


7-5-2022 Food Truck Ordinance

See Link for Food Truck Ordinance

7-5-2022 Food Trucks

FOOD TRUCK ORDINANCE

TOWN OF MONTROSE

7-5-2022

FOOD TRUCKS, TRAILERS, CARTS NOT ALLOWED ON ANY PUBLIC PROPERTY WITHIN THE TOWN.

FOOD TRUCKS, TRAILERS, CARTS ALLOWED ON PRIVATE PROPERTY BUT CANNOT BE IN THE PUBLIC ROAD RIGHT-OF-WAY.  SERVING WINDOW CANNOT FACE ROADWAY.

HOURS OF OPERATION - 5 AM- 9 PM.

NOISE LIMIT - 60 DECIBELS.


STH 69 Construction Project Update 6/16/22

The STH 69 project is making some great progress with the drier weather this week.

STH 69 from Manhattan Drive to Pine Row will CLOSE on June 27th for bridge work on the Badger Mill Creek Bridge. Message boards will be placed at both intersections on June 20th for advanced warning.  Access to Manhattan Drive will be from one of the roadways to the south.

A reminder that CTH PB at STH 69 in Paoli is closed.  

Construction Update for STH 69 and the upcoming weeks:

  • Existing topsoil is being stripped off
  • Grading operations are occurring and will continue over the next several months as the contractors build the new roadway core.
  • The lanes are narrow as crews work on and through the existing roadbed.
  • Bridge work will begin June 27th on the Badger Mill Creek bridge
  • Utility work continues south of Paoli to Belleville

STH 69 is closed to thru traffic.  Access is allowed for residents and businesses that have an origin or destination on the project. It is highly suggested to use your closest access to STH 69 to get to a driveway. Large trucks need to use appropriate truck routes.

Please slow down, and the construction crew has the right-of-way.

A signed detour route is posted and follows WIS 92, WIS 78 and US 18/151.

Project Website:  https://projects.511wi.gov/wis69/

If you have any comments or questions, please reach out to Kim Ballweg at 608.212.5191 or ballwegk@AyresAssociates.com.

Thank you for your patience and understanding throughout the construction season.


Emergency Shelter and Cooling Centers

The American Red Cross will continue to offer shelter through this evening at Madison College for those displaced by this week’s severe weather.

 

Additionally, Dane County will re-open the Veterans Memorial Coliseum at the Alliant Energy Center tomorrow from 10am until 5pm to serve as a cooling center.

 

Extreme heat is forecast to continue for the next 24 hours. Meanwhile, utility crews continue to work to restore power to those who lost electricity in Monday’s severe storms.

 

 The area may be impacted by additional severe thunderstorms tomorrow, (Wednesday, June 15th).

 

 Residents are encouraged to continue to monitor websites, social media, and local media outlets for further updates.  Health safety information is available at Public Health Madison Dane County’s website – https://www.publichealthmdc.com/alerts/extreme-heat-on-june-14-and-15.


STH 69 Construction Project Update 5/31/22

Spring wet weather has slowed progress somewhat, but a nice stretch of weather appears in the forecast this week!

CTH PB at STH 69 in Paoli with close completely to traffic on June 6th.  Message boards are in place today for advanced warning. The detour is posted. Work will begin to build the new roundabout in the coming weeks.

Construction Update for STH 69 and the upcoming weeks:

  • Existing topsoil is being stripped off.
  • Grading operations are occurring and will continue over the next several months as the contractors build the new roadway core.
  • Building of the subgrade and lower rock layers has begun south of Riverside Drive
  • Installation of new drainage culvert pipes continues
  • Utility work continues south of Paoli to Belleville

STH 69 is closed to thru traffic.  Access is allowed for residents and businesses have an origin or destination on the project. It is highly suggested to use your closest access to STH 69 to get to a driveway. Large trucks need to use appropriate truck routes. The lanes are narrow as crews work on and through the existing roadbed. Please slow down, and the construction crew has the right-of-way.

A signed detour route is posted and follows WIS 92, WIS 78 and US 18/151.

Project Website:  https://projects.511wi.gov/wis69/

If you have any comments or questions, please reach out to Kim Ballweg at 608.212.5191 or ballwegk@AyresAssociates.com.

Thank you for your patience and understanding throughout the construction season.


No Trash Pickup Monday-Memorial Day

Pellitteri Home Page

 

 

 

No Trash & Recycling Pick-up on Memorial Day

 

We will be closed on Monday, May 30th in observance of Memorial Day.

Residents will be serviced one day later than their normal service day during the week of May 30th to June 3rd.

Residents normally serviced on Friday will be serviced on Saturday, June 4th.

Since collection routes may be serviced differently, your pick-up time may be altered. As always, please make sure to have your carts out by the time designated by your community (click here for more information).

Placing your trash in bags prior to putting them in your cart helps to cut down on wind-blown litter and allows for easier clean-up and disinfecting if carts tip over. For recyclables, use only see-through plastic bags. (Recyclable items placed in black bags will not be recycled. See our website for more details about contamination.)


STH 69 Construction Project Update 5/13/22

The weather was very warm this week, it was nice and dry to allow for some construction work to really start occurring!

 CTH PB at STH 69 in Paoli with close completely on May 31st.  Message boards will be placed on May 24th for advanced warning. The detour is posted. Work will begin to build the new roundabout.

 Construction Update for STH 69 and the upcoming weeks:

  • Existing topsoil is being stripped off.
  • Grading operations are occurring and will continue over the next several months as the contractors build the new roadway core.
  • Installation of new drainage culvert pipes continues
  • Utility work continues south of Paoli to Belleville

 STH 69 is closed to thru traffic.  Access is allowed for residents and businesses have an origin or destination on the project. It is highly suggested to use your closest access to STH 69 to get to a driveway. Large trucks need to use appropriate truck routes. The lanes are narrow as crews work on and through the existing roadbed. Please slow down, and the construction crew has the right-of-way.

 A signed detour route is posted and follows WIS 92, WIS 78 and US 18/151.

 Project Website:  https://projects.511wi.gov/wis69/

If you have any comments or questions, please reach out to Kim Ballweg at 608.212.5191 or ballwegk@AyresAssociates.com.

Thank you for your patience and understanding throughout the construction season.